Dade City, Florida - GV19-0357

Dec. 22, 2019 - Jan. 5, 2020

Build Details
Work schedule: weather permitting Monday-Friday (except holidays ) 8-3 (Saturdays optional 9-2)
Type of work: 6-8 New Construction homes throughout our build season. build site prep, blocking, framing, dry in home, siding, drywall, trim & doors, painting, flooring, cabinets, deconstruct likely, restore projects as needed, whatever the affiliate needs done
Parking location: marked spaces at our Lake Thomas Habitat for Humanity RV Campground 14431 Rozar Court, Dade City, FL
Parking fee per night: $16.00
Hookups: Electric: 50 amp, Water: at rig, Sewer: at rig
Max Rig Size: 44'
Miles to job site: < 5 miles
Spaces available: 12 of 14
Team leader:

To apply for this build, please fill out the online registration form.